As the City of Ottawa continues to expand, more challenges are encountered given that the prime land has been developed and the remaining developable land has more restrictive characteristics such as flood plain restrictions and environmental habitat considerations.

In the case of the Mattamy Homes Half Moon Bay West and Glenview Homes Flagstaff subdivisions, an existing channel that primarily served to convey flows from the swamp of the Cambrian Woods to the Jock River had to be realigned. The realigned channel would replace the old conveyance route, while providing a travel corridor and habitat for frogs between the swamp and the river. The new channel was required to pass under Flagstaff Drive, a main roadway within the subdivisions. In order to pass the 100-year flows the hydraulic design of the channel required twin 800 mm diameter culverts.

RELATED: 100-Year-Old Thunder Bay Dam Refurbished with Precast Elements

Given the importance of this roadway, precast was selected as the material of choice to ensure the maximum service life of this critical infrastructure. A precast concrete box culvert with a 1200 mm span by 900 mm rise was selected. The culvert was produced and designed by M CON Products Inc. of Ottawa, according to OPSS 1821 standard as well as CHBDC. The overall length of the structure would be 32.5 m with a total of 13 pieces.

Due to the dual purposes of the culvert to both convey flow and provide a travel corridor for frogs, the culvert included a unique design feature. It was decided to add a 300 mm x 150 mm shelf inside the culvert along its entire length to allow frogs to traverse the corridor in high flow conditions.

M CON Product’s engineering and fabrication teams were able to design the required shelf and fabricate the necessary formwork to achieve the secondary casting which resulted in the creation of an amphibian shelf within the precast concrete box culvert.

DSEL would like to thank M CON Products Inc. for their ability to provide timely design and manufacturing solutions that addressed both the environmental challenges of this development as well as keeping the project on schedule.

Matthew Coles, CAN-CISEC
Project Manager
DSEL
Precast Producer: M CON Products Inc.

RELATED ARTICLES

This Culvert Collapse Could Easily ...

A corrugated steel culvert collapsed under the weight of a school bus in Rhome, Texas ...

m con products

M CON Products Inc. Manufactures ...

A new development in Barrhaven, Ontario (just south of Ottawa) needed a bridge structure to ...

Municipal and Consulting Inspector Information ...

As part of our vision on education, the Canadian Concrete Pipe and Precast Association is ...