Trafalgar Accelerated Bridge and Culvert Construction

Share
  • Share on Twitter
  • Share on Facebook
  • Share on Linkedin
Trafalgar-project

The below footage shows bird’s eye footage of a three-week construction project under Trafalgar Road completed in Oakville, Ontario in a high-traffic zone.

The New Communities of Oakville will be home to 50,000 people, create nearly 35,000 jobs, and include residential, commercial, employment, institutional and natural open spaces. Stormwater management is a top priority when it comes to large developments. This project required a 92m bridge/culvert under Trafalgar Road, a highly used, important route for many people in the area.

RELATED: Ormston Subdivision: From Cast in Place to Precast

The road could not be closed during the installation of this bridge/culvert and no delays for construction would be accepted. DECAST manufactured all components weeks in advance and delivered precast footings and DE-SPAN®s exactly when the contractor required them. To excavate, install 27 precast footings, install the 40 DE-SPAN®s, backfill and pave (leaving one half of the road open at all times) took only 22 days.

RELATED ARTICLES

concrete-pipe

Tutorial: PipePac Indirect Design Method

In this video, you will learn the basics of the Indirect Design Method, and also ...

Graphic cover image featuring large concrete pipes in the foreground and a faint map of Canada in the background. The text reads “Canada’s Concrete Infrastructure – From Coast to Coast” with the CCPPA logo above. A red line traces a route across the country from the Pacific to the Atlantic, symbolizing national infrastructure connection.

From Coast to Coast Video

A look into Canada's precast concrete industry through this coast-to-coast video highlighting the people, processes, ...

concrete pipe durability

Pipe sample from 1842 shows ...

Are you still wondering what is the service life of a concrete pipe? Is it ...